Our Progress
September-2023Chairman Sukh Chayn Residence participated in a tree plantation activity
CHAIRMAN Sukh Chayn Residence personally plants 60 trees for the environment surrounding the main access road- Access road & road sleeve works initiated
- Waterproofing for ground floor garden base initiated
- Guard house work completed
- Smart Building Management System ready for deployment
- Swimming pool area finishing works, airconditioning outers & indoor cassette installation are progress
- Kitchen fixture & fitting works halted due to delay in equipment resumes
- Bus Bar System installation
- Meter installation by IESCO
August-2023Progress of Finishing Works
OTIS elevators and transformers arrived on site & installation work initiated.
Water pump and Firefighting pumps received on site and installation work initiated.
Reception area glass ceiling Installation completed.
Reception Area finishing works in progress.
CAFÉ’ Area Finishing works completed. Community Hall Finishing works completed.
Swimming pool water-line works completed.
Gym area finishing works nearing completion.
Main drop-off area civil works in active progress.
Access road to main entrance development work in progress.May-2023Government lifts ban on imports and supply resumes
April-2023Mr. Saleh Azeem is honored as the youngest recipient of Tamgha-e-Imtiaz
CEO Sukh Chayn Residence Mr. Saleh Azeem is honored as the youngest recipient of Tamgha-e-Imtiaz (medal of excellence) for being at the forefront of establishing innovative and sustainable projects for the betterment of the construction industry of Pakistan and in recognition for his public services to the flood affectees by building 100 homes, an infirmary and a school within 30 days. (THE NATION)
February-2023Prolonged import ban and unexcepted port closure further delays
- Apartment window installation completed
- Ceiling works of Apartments completed
- Apartment base coat paint works completed
- Apartment doors & fittings completed
- Installation of kitchen fixtures & fittings suspended pending import
- Swimming Pool works initiated regardless of delay in ACP supply
- Reception & Main Lobby area finishing works initiated pending completion of ALUCOBOND installation above
- Gym Area Finishing works Initiated
- Community Area finishing works initiated
- CAFE’ area finishing works initiated
October-2022Ban on import persists, delaying the supply of vital equipment & machinery
- Apartment window installation nearing completion
- Ceiling work of Apartments nearing completion
- Apartment base coat paint works nearing completion
- Apartment doors & fittings installation in progress
- Installation of kitchen fixtures & fittings suspended due to delay in supply for complimenting works
- Installation of washroom and shower fixtures & completed
- Alucobond Fire rated Aluminum composite Panel Installation in progress
June-2022Progress of Finishing Works
- Plumbing Line works completed
- Firefighting line works completed
- Air conditioning duct works completed
- Apartment window installation in progress
- Apartment window installation in progress
- Apartment Door Installation initiated
- Installation of kitchen fixtures & fittings initiated
- Installation of washroom and shower fixtures & fittings initiated
- Cabinetry works initiated
- Smart Building Management System development initiated
- Government of Pakistan Ministry of Commerce under S.R.O.598(I)/2022, imposes ban on imports May 2022 effecting supply of import of vital equipment for Sukh Chayn Residence
February-2022Progress of Finishing Works
- Main Entrance (Under Construction)
- EPS wall partitions construction completed (Ground to 11th Floor)
- Electrical works including data networks (In active progress: As high as the 5th & 6th Floor)
- Plumbing Line works (In active progress: As high as the 5th Floor)
- Water Line works (In active progress: As high as the 5th Floor)
- Fire Fighting & Fire Sprinkler Line work in active progress
- Perimeter wall & Entry/Exit gates (under construction)
October-2021Progress of Finishing Works
· EPS Wall Partitioning Works In Final Stages · Parking Basement Finishing Work In Progress · Finishing works In Active Progress: o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network LinesAugust-2021Grey Structure Construction Completed
June-2021World Renowned Samsung Selected For Air Solutions
May-2021Internal EPS Wall Partitioning Work Active
April-2021Twelfth Floor Construction Complete
February-2021Tenth Floor Construction Complete
January-2021Finishing Works Initiated
o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network Lines
December-2020Ninth Floor Construction Complete
October-2020Eighth Floor Construction Complete
September-2020Seventh Floor Construction Complete
August-2020Sixth Floor Construction Complete
July-2020Fifth Floor Construction Complete
June-2020Fourth Floor Construction Complete
May-2020Third Floor Construction Complete
March-2020Second Floor Construction Complete
January-2020First Floor Construction Complete
December-2019Ground Floor Construction Complete
August-2019First Basement Construction
May-2019Second Basement Construction
January-2019Third Basement Construction
February-2019Raft Foundation Completed
Major milestone completed with the completion of the final concrete pour for the Raft Foundation. About a quarter of all the concrete for the building sits in the Raft Foundation.1-January-2019Sukh Chayn Residence Launches New 1 & 2 Bedroom Apartments
02-December-2018Water Proofing & Raft Foundation Construction
01-December-2018Excavation Completed
01-May-2018Ground Breaking & Excavation
30-April-2018Sukh Chayn Residence Launched
6-April-2018CDA Issues NOC
June-2017Design Contract Awarded To ASA
5-May-2017Certificate of Possession
March-2017Vision of the Building shared with Top Architects
12-Dec-2016CDA Auction
Plot #6, 10th Avenue, F-10/4 CDA Press Release
Sukh Chayn Pvt. Ltd. wins bid.