February-2022Progress of Finishing Works
- Main Entrance (Under Construction)
- EPS wall partitions construction completed (Ground to 11th Floor)
- Electrical works including data networks (In active progress: As high as the 5th & 6th Floor)
- Plumbing Line works (In active progress: As high as the 5th Floor)
- Water Line works (In active progress: As high as the 5th Floor)
- Fire Fighting & Fire Sprinkler Line work in active progress
- Perimeter wall & Entry/Exit gates (under construction)
October-2021Progress of Finishing Works
· EPS Wall Partitioning Works In Final Stages · Parking Basement Finishing Work In Progress · Finishing works In Active Progress: o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network LinesAugust-2021Grey Structure Construction Completed
June-2021World Renowned Samsung Selected For Air Solutions
May-2021Internal EPS Wall Partitioning Work Active
April-2021Twelfth Floor Construction Complete
February-2021Tenth Floor Construction Complete
January-2021Finishing Works Initiated
o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network LinesDecember-2020Ninth Floor Construction Complete
October-2020Eighth Floor Construction Complete
September-2020Seventh Floor Construction Complete
August-2020Sixth Floor Construction Complete
July-2020Fifth Floor Construction Complete
June-2020Fourth Floor Construction Complete
May-2020Third Floor Construction Complete
March-2020Second Floor Construction Complete
January-2020First Floor Construction Complete
December-2019Ground Floor Construction Complete
August-2019First Basement Construction
May-2019Second Basement Construction
January-2019Third Basement Construction
February-2019Raft Foundation Completed
Major milestone completed with the completion of the final concrete pour for the Raft Foundation. About a quarter of all the concrete for the building sits in the Raft Foundation.1-January-2019Sukh Chayn Residence Launches New 1 & 2 Bedroom Apartments
02-December-2018Water Proofing & Raft Foundation Construction
01-December-2018Excavation Completed
01-May-2018Ground Breaking & Excavation
30-April-2018Sukh Chayn Residence Launched
6-April-2018CDA Issues NOC
June-2017Design Contract Awarded To ASA
5-May-2017Certificate of Possession
March-2017Vision of the Building shared with Top Architects
12-Dec-2016CDA Auction
Plot #6, 10th Avenue, F-10/4 CDA Press Release
Sukh Chayn Pvt. Ltd. wins bid.