Our Progress

  • February-2022Progress of Finishing Works

    Our Progress

    Basement 1, 2 & 3 finishing works (75% complete)

    • Main Entrance (Under Construction)
    • EPS wall partitions construction completed (Ground to 11th Floor)
    • Electrical works including data networks (In active progress: As high as the 5th & 6th Floor)
    • Plumbing Line works (In active progress: As high as the 5th Floor)
    • Water Line works (In active progress: As high as the 5th Floor)
    • Fire Fighting & Fire Sprinkler Line work in active progress
    • Perimeter wall & Entry/Exit gates (under construction)
  • October-2021Progress of Finishing Works

    · EPS Wall Partitioning Works In Final Stages · Parking Basement Finishing Work In Progress · Finishing works In Active Progress: o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network Lines
  • August-2021Grey Structure Construction Completed

    Our Progress

    Grey Structure Construction Completed

  • June-2021World Renowned Samsung Selected For Air Solutions

    Our Progress

    Samsung For Air Solutions

  • May-2021Internal EPS Wall Partitioning Work Active

    Our Progress

    EPS Partitioning Work Active

  • April-2021Twelfth Floor Construction Complete

    Our Progress

    Twelfth Floor Construction Complete

  • February-2021Tenth Floor Construction Complete

    Our Progress

    Tenth Floor Construction Complete

  • January-2021Finishing Works Initiated

    o Fire Fighting Lines o Water Lines o Plumbing Lines o Electrical Lines o Data Network Lines
  • December-2020Ninth Floor Construction Complete

  • October-2020Eighth Floor Construction Complete

    Our Progress

    Eighth Floor Construction Complete

  • September-2020Seventh Floor Construction Complete

    Our Progress

    Seventh Floor Construction Complete

  • August-2020Sixth Floor Construction Complete

    Our Progress

    Sixth Floor Construction Complete

  • July-2020Fifth Floor Construction Complete

    Our Progress

    Fifth Floor Construction Complete

  • June-2020Fourth Floor Construction Complete

  • May-2020Third Floor Construction Complete

  • March-2020Second Floor Construction Complete

  • January-2020First Floor Construction Complete

  • December-2019Ground Floor Construction Complete

  • August-2019First Basement Construction

  • May-2019Second Basement Construction

  • January-2019Third Basement Construction

  • February-2019Raft Foundation Completed

    Major milestone completed with the completion of the final concrete pour for the Raft Foundation. About a quarter of all the concrete for the building sits in the Raft Foundation.
  • 1-January-2019Sukh Chayn Residence Launches New 1 & 2 Bedroom Apartments

  • 02-December-2018Water Proofing & Raft Foundation Construction

  • 01-December-2018Excavation Completed

  • 01-May-2018Ground Breaking & Excavation

  • 30-April-2018Sukh Chayn Residence Launched

  • 6-April-2018CDA Issues NOC

    Our Progress

    CDA Approves Building Plan for Sukh Chayn Residence

  • June-2017Design Contract Awarded To ASA


  • 5-May-2017Certificate of Possession

    Our Progress

    Full payment made to CDA and possession signed over to Sukh Chayn Valley Pvt. Ltd.

  • March-2017Vision of the Building shared with Top Architects

  • 12-Dec-2016CDA Auction

    Plot #6, 10th Avenue, F-10/4 CDA Press Release
    Sukh Chayn Pvt. Ltd. wins bid.